On a biweekly basis, we will post an update with the construction work in the coming weeks and when we expect any inconveniences. Updates are always accompanied by an app in the A Lab Whatsapp Group or an email.
Current projects:
- Renovation of basement studio space The work is expected to be completed in November. After this, A Lab will also make some adjustments and investments. The goal is to have the space operational by January 1, 2026.
- Repair of jointing on the Overhoeksplein / Badhuiskade facade Work will start at the end of August 2025 and is expected to be completed by the end of 2025.
Do you have any questions, feedback or ideas? Let us know!
General policy for construction works in A Lab
- The area of the work has been closed and classified as a construction site. Access is not allowed unless accompanied by one of the builders or someone from the A Lab Team.
- Substantial noise may be made on weekdays between 07:00 h and 10:00 h. Outside these times, noise pollution is not allowed unless reported at least two weeks in advance.
Planned work in the coming weeks:
Weeks: Mon, August 25 to Sun, August 31
Electric installation
Hanging cable trays, adjustments to existing installation
Expected inconvenience: ceiling drilling between 07:00AM and 10:00AM.
Installation of new partition walls
The new walls will be erected and finished. Expected disruption: drilling work on the ceiling between 7:00 a.m. and 10:00 a.m.
Weeks: Mon, Sept 01 to Sun, Sept 07
Electric installation
Hanging cable trays, adjustments to existing installation
Expected inconvenience: ceiling drilling between 07:00AM and 10:00AM.
Installation of new partition walls
The new walls will be erected and finished. Expected disruption: drilling work on the ceiling between 7:00 a.m. and 10:00 a.m.